Infrastructure

Infrastructure

Power Plants

Power Plants

2 steam boilers ensure the supply with high-pressure and medium-pressure steam and produce part of the power needed

 
Power Supply

Power Supply

Electrical power is supplied at the voltage levels
35 kV, 5 kV, 500 V, 380/220 V, and 42 V. 3 steam networks (low-pressure, medium-pressure, high-pressure), 3 water networks, and 6 cooling plants are available

 
Gas Networks

Gas Networks

Ethylene networks (90, 40, and 20 bar), propylene, hydrogen (15 and 150 bar), fuel gas, pressurized air, measuring air, nitrogen (6, 40, and 200 bar), oxygen, coke-oven gas

 
Further Pipeline Networks

Further Pipeline Networks

Access to 2 crude oil pipelines, to the north-west European ethylene network and to the propylene pipeline to and from the port of Duisburg , pipeline connections for nitrogen, hydrogen, oxygen, coke-oven gas, further product pipelines to customers in the region

 
Waste Disposal

Waste Disposal

Solutions for your waste water and waste disposal problems

 
Port

Port

Scholven is connected to the ports of Horst, Bottrop, and Marl via pipeline

 
Railroad Network

Railroad Network

15 km of railroad network at the site with access to the railroad network of Deutsche Bahn

 
Road Network

Road Network

Direct access to the highway A52 (B224) and thus to the European highway network

 
Telecommunications

Telecommunications

Provision of high-performance networks and communications solutions. Installation and maintenance of workplace equipment, adaptation of interfaces

 
 